.

 



Volume: 24, Issue: 3 - 02/16/2026

 

Bids on public construction contracts are typically completed in the final minutes before bid submittal. Price quotations from trade subcontractors are not received until then, leaving no time to negotiate a subcontract agreement. The bidder on the prime contract relies on the subcontractor quote and, if awarded the prime contract, expects the sub to perform at that price.

 

An electrical subcontractor in Washington State tried to back out of its price quotation after bid opening. The sub’s proposal had stated that written acceptance was required within seven days of receipt. The bidder had not accepted in writing but had incorporated the price into its successful bid. The subcontractor argued that any reliance by the bidder had not been reasonable in light of the lack of acceptance.

 

The second case in this issue involves qualification to provide expert opinion regarding an architect’s professional standard of care. The South Carolina Supreme Court ruled that under state law, a professional engineer’s testimony would be acceptable. The engineer had chosen, however, to offer only an opinion regarding construction contract administration, not an architect’s professional design responsibilities.

 

The third case addresses commercial general liability (CGL) insurance coverage for subcontracted work. Under the terms of a contractor’s CGL policy, there was coverage only if the subcontract was in writing and the subcontractor had proof of its own CGL coverage.


 

Although a subcontractor price quotation stated it was conditioned on written acceptance within seven days of receipt by the bidder on a public contract, the price became binding on the sub despite the bidder’s lack of written acceptance.


 

A state statute required an affidavit from a qualified expert in order to proceed with a professional negligence action. The statute did not require the expert to possess the same professional license as the defendant.


 

A Commercial General Liability insurance policy was not ambiguous. An endorsement made coverage for subcontractor acts contingent upon a written subcontract agreement and certain subcontractor insurance requirements.


Volume: 24, Issue: 2 - 01/30/2026

 

Contractor recovery of unabsorbed home office overhead, incurred during a period of suspended work, is a creature of federal construction contracts and the federal court system. The use of the Eichleay formula to calculate these damages is mandatory. The issue of unabsorbed overhead has gradually seeped into non-federal construction contracting and has been addressed by state courts. Some state courts, but by no means most, have expressly endorsed the use of the Eichleay formula.

 

A Louisiana appeals court was recently confronted with this issue. Eichleay had been occasionally discussed by that state’s courts but never expressly endorsed or disallowed. The appeals court allowed contractor recovery of unabsorbed home office overhead to stand. Award of these damages was within the proper discretion of the trial court.

 

The other case in this issue involves a wrongfully terminated subcontractor’s right to payment for the value of its work from the project owner. The sub could not recover in quantum meruit because it had worked under an express agreement with the prime contractor. The project owner was a third-party beneficiary of that agreement.


 

State law did not mandate contractor recovery of unabsorbed home office overhead calculated according to the Eichleay formula. But, award of those damages was within the discretion of the trial court.


 

An unpaid subcontractor, having failed to perfect its mechanic’s lien, could not recover for the value of its work from the project owner. “Quantum meruit” was not available because the work had been subject to an express contract with the prime contractor.


Volume: 24, Issue: 1 - 01/15/2026

 

When a contractor settles its claims with the project owner, the proceeds are frequently insufficient to cover payment of all parties on the project. Contractors need to be aware that mechanic’s lien statutes in many states impose a trust on these settlement proceeds for the benefit of unpaid subcontractors and suppliers.

 

The prime contractor on a commercial project in New York advanced funds to its subs and suppliers during the construction process. It paid invoices for work and equipment for which the contractor had not received payment from the project owner. The contractor eventually settled its claims with the owner and attempted to reimburse itself for these advances but discovered it did not have unfettered discretion over the settlement funds.

 

The second case in this issue addresses a consulting engineer’s reluctance to express an opinion on the value of a contractor’s suspension of work claim against the project owner. The construction contract assigned this responsibility to the engineer. The engineer’s reticence placed the owner in breach of the construction contract.

 

The third case involves a public project owner’s refusal to consider a bid because the bidder failed to submit two original bid forms. Alabama’s highest court said the contractor was entitled to a court hearing on the propriety of the bid exclusion.


 

A contractor could not, without a court order, use settlement funds received from the project owner to reimburse itself for funds it had advanced to subcontractors and suppliers during performance of the work.


 

A public project owner’s failure to compel its consulting engineer to make a determination called for in the construction contract was a breach of that contract.


<< PREVIOUS PAGE   Page: 1 of 298   NEXT PAGE >>

 

 

 


WPL
PUBLISHING CO, INC.
WPL Publishing - 5750 Bou Avenue #1712 - Rockville, MD 20852

Phone: (301)983-0443  -  Fax: (301)983-4367

All Content and Design Copyright © 2026 WPL Publishing
About Us

Contact Us

Privacy Policy

My Account